|
AKS should be
installed to structures in the longest possible vertical panels to limit
horizontal joints.
The sheets must be well secured against the formwork to avoid movement or
displacement when the concrete is poured. Double sided adhesive tape is
available from AKS Lining Systems for temporary fixing of AKS to
formwork.
Care must be taken to avoid damage to the lining, as any damage will need to
be located and repaired. The use of nails to secure AKS to the formwork is
to be avoided, as it is extremely difficult to find these penetrations at a
later stage.

>
Cut all of the AKS sheets to the required sizes as indicated on the cutting
schedule.
> Set the sheets up vertically, with the smooth side fixed
to the inner face of the formwork, prior to pouring the concrete.
> To ensure that the sheets do not move during casting and
that no concrete is deposited between the formwork and the sheet, one of the
following procedures should be followed:
- Glue the sheet to the face of the formwork
with contact adhesive.
- Clamp the sheets to the formwork along
their top edge, above the level of the concrete to be poured. Nails should
not be used as it is difficult to locate the penetration holes at a later
stage. Any penetration through the liner must be clearly marked for later
repair.
- Nylon fishing line can be used to hold the
AKS in position. By lacing the last row of knobs along the edge of the
sheets, the sheets can then be tensioned together.
- Double-sided tape can also be used to hold
AKS against wooden formwork.
- An "H" profile with a "tear-off" front
strip is recommended as a measure to properly align the AKS sheets prior
to and during the casting process. The "H" profile is available as an AKS
accessory.
- The AKS lining will be pressed against the
face of the formwork by the spacers fitted to steel reinforcement, prior
to pouring the concrete. A few knobs may be removed/trimmed to allow
clearance for the spacers, or smaller spacers can be used against the
knobs to ensure correct positioning of the reinforcement.
- It is common for concrete contractors to
use ties between their shutters to establish correct wall thickness, etc.
Our preferred procedure, however, is to avoid all penetrations through the
liner, as far as possible, in favour of external bracing of the formwork.
- Once AKS and shuttering is place, the
concrete is poured.
>
Cut AKS lining to accurate size to avoid gaps at joints then place AKS on
top of the soffit formwork with the anchor knobs facing upwards

>
Any hatches, manholes or other penetrations through the concrete slab must
be "boxed out". The vertical side of these penetrations must be AKS lined.
- The sheets can be fixed to the adjacent
reinforcement or supported by foam in the intended openings.
- The best procedure is to prefabricate
these opening details.
- Knobs which clash with each other at the
corner of the 90o joint may be removed using side cutters.
> All joints in the AKS are
to be sealed before concrete is poured to avoid gaps through which "fines"
may flow. Adhesive tape or our "H" profile can be used for this purpose.
> Pre-cut all AKS floor
panels and position them "dry" to ensure that the gaps between adjacent
sheets on the floor and between floor/wall sheets do not exceed 3,0mm. "H"
profiles may also be used for proper alignment of these sheets and to keep
joints as clean as possible for final welding.
> Areas of the floor are marked out in panels to receive
the AKS lining and a modified cement primer is applied to this surface using
a broom or block brush. The cement modifier is discussed later in this
section dealing with the lining of existing structures.
> Once the primer is "tack dry" the special grout is
placed/poured in a 12mm thick layer onto the concrete floor.
> The pre-cut panels of AKS are carefully rolled into the
wet grout to ensure that air is not trapped beneath it. The anchor knobs
automatically form a 12mm space for the grout. Please note that the AKS
finished surface will follow the surface of the concrete beneath it. Care
must be taken to ensure that the concrete surface is level and smooth to
achieve best results.

> The AKS must be ballasted
over 100% of its area immediately after it is placed into the grout.
Isolated loads may cause unevenness of the surface, so take care to position
weights on planks or pallets, or position bricks or building blocks evenly
over the surface. The ballast must be left in place until the grout has set.
> Care should be taken to wipe away any grout that has
squeezed up between the joints whilst the grout is still green. As soon as
the initial set of the grout has taken place, the grout must be raked out of
the joints between the adjacent panels to the width of the gap and depth of
the lining.
Should any air remain trapped under the
sheet, this may be repaired by drilling two small holes (one at each end of
the cavity) and injecting grout into the cavity through the one hole until
it squeezes out of the other. These holes must be clearly marked for repair
by extrusion welding.
|